The Seller under CIF Contract applied to Interlegal; it delivered goods to the Buyer within the prescribed supply period and performed all the other appropriate terms of the Contract.

The Client applied for refund of costs paid as demurrage in favor of the Shipowner.

According to the Contract, the Buyer shall pay for the goods within 48 days from the date of receiving contractual documents by the bank; however, the Buyer could pay for the goods just a few days later, for its own reasons.

Having studied all the case circumstances, Interlegal lawyers sent a claim to the Buyer with a demand to reimburse costs paid as demurrage. With no reply, lawyers recommended the Client to apply to the arbitration.

Just after initiating arbitration proceedings, the Buyer proposed a pretrial dispute settlement. The Parties agreed that the Seller will receive paid costs, while arbitration proceedings terminated.

As famous and experienced market players, the Parties understood all the risks of applying to arbitration for charging a small amount. In the Seller’s opinion, the most optimal way was to recover demurrage in the form of further contracts, without time/cost spending for arbitration proceedings. The Buyer also understood and supported the Seller’s unwillingness to pay arbitration & legal fees with freezing funds.

Due to step-by-step actions, detailed analysis and clear strategy, Interlegal lawyers restored and implemented the Client’s contractual and lawful rights.

Interlegal law team led the case: junior lawyers Denys Bakaiev and Larysa Karakach, managed by partner Alexey Remeslo

  • The Buyer failed to fulfill its financial obligations within deadline prescribed by the contract2024.05.23

    A client, seller who entered into contracts with two companies of the same group, applied to Interlegal. The contracts provided supply o...

    show more
  • Limassol Boat Show 20242024.05.15

    We are pleased to announce that on 23-26 May Interlegal will be participating in the ninth edition of the largest boat show in the Eas...

    show more
  • General average due to collision of vessels. What should the cargo owner do?2024.03.18

    Expansion of geography to the Caspian states was and is one of the goals of our company development. Therefore, we are particularly plea...

    show more
  • Misunderstanding and technical errors as the reason for dispute2024.02.12

    A company applied to Interlegal for carrying out claims handling with their counterparty. Due to a simple misunderstanding, business rel...

    show more
  • What are the legal effects of delivering goods of poor quality under CIF contract?2024.02.05

    The Client applied to Interlegal for analysis of potential consequences of delivering mineral fertilizers of poor quality in the framewo...

    show more
  • UPD: what to do if arrest fails at the first time?2023.11.30

    Fresh news by Interlegal: one of the most interesting latest ship arrests! Let us remind: A Cypriot company filed to Interlegal a req...

    show more
  • Bank request again: additional documents and explanations2023.11.20

    Now in the process of transactions banks often asks our Clients to provide documents certifying lawful payment, mainly agreement between...

    show more
  • Forgive and forget: is small demurrage a reasonable excuse for arbitration proceedings?2023.10.26

    The Seller under CIF Contract applied to Interlegal; it delivered goods to the Buyer within the prescribed supply period and performed a...

    show more
  • Freight management flaws: incorrect notices or disputed claims2023.10.23

    Recently, Interlegal law team defended the Client’s interests in a dispute regarding incorrectly calculated demurrage. The case concerne...

    show more
  • Interlegal obtained FOSFA award in favor of the Client in the amount exceeding 4 million USD2023.10.16

    The Client applied to our law team due to non-performance of contract terms, i.e. non-payment for the goods. Parties to the contract...

    show more