A client, seller who entered into contracts with two companies of the same group, applied to Interlegal. The contracts provided supply of over 26,000 metric tons of Ukrainian corn. However, the buyers failed to fulfill their financial obligations within deadline prescribed by the contract.

After several attempts to negotiate and to settle the situation, the seller was forced to agree on changing terms of the contract by signing a supplementary agreement on providing a discount to buyers in case of payment of the agreed amount within the prescribed period.

Despite this, the buyers paid the agreed amount later than the set deadline, thus voiding supplementary agreement. That is, the parties returned to initial terms of the contract. It means that the discount was cancelled, and the seller issued an invoice on the discount amount exceeding 500,000 US dollars. The invoice currently remains unpaid, but Interlegal team knows what to do in such cases.

If the invoice is unpaid within the additional set period, our team will represent the seller in GAFTA arbitration.

This case is a vivid example of the impact of economic pressure on contractual relations within international trade. The buyer’s failure to fulfill their obligations in due time forced the seller to take financial risks and to accept new terms of the contract.

Further case consideration will be posted later. If you follow updates on our social media, you will not miss anything interesting.

  • The Buyer failed to fulfill its financial obligations within deadline prescribed by the contract2024.05.23

    A client, seller who entered into contracts with two companies of the same group, applied to Interlegal. The contracts provided supply o...

    show more
  • Limassol Boat Show 20242024.05.15

    We are pleased to announce that on 23-26 May Interlegal will be participating in the ninth edition of the largest boat show in the Eas...

    show more
  • General average due to collision of vessels. What should the cargo owner do?2024.03.18

    Expansion of geography to the Caspian states was and is one of the goals of our company development. Therefore, we are particularly plea...

    show more
  • Misunderstanding and technical errors as the reason for dispute2024.02.12

    A company applied to Interlegal for carrying out claims handling with their counterparty. Due to a simple misunderstanding, business rel...

    show more
  • What are the legal effects of delivering goods of poor quality under CIF contract?2024.02.05

    The Client applied to Interlegal for analysis of potential consequences of delivering mineral fertilizers of poor quality in the framewo...

    show more
  • UPD: what to do if arrest fails at the first time?2023.11.30

    Fresh news by Interlegal: one of the most interesting latest ship arrests! Let us remind: A Cypriot company filed to Interlegal a req...

    show more
  • Bank request again: additional documents and explanations2023.11.20

    Now in the process of transactions banks often asks our Clients to provide documents certifying lawful payment, mainly agreement between...

    show more
  • Forgive and forget: is small demurrage a reasonable excuse for arbitration proceedings?2023.10.26

    The Seller under CIF Contract applied to Interlegal; it delivered goods to the Buyer within the prescribed supply period and performed a...

    show more
  • Freight management flaws: incorrect notices or disputed claims2023.10.23

    Recently, Interlegal law team defended the Client’s interests in a dispute regarding incorrectly calculated demurrage. The case concerne...

    show more
  • Interlegal obtained FOSFA award in favor of the Client in the amount exceeding 4 million USD2023.10.16

    The Client applied to our law team due to non-performance of contract terms, i.e. non-payment for the goods. Parties to the contract...