The Client applied to our law team due to non-performance of contract terms, i.e. non-payment for the goods.

Parties to the contract were Cypriot and Swiss residents who agreed on sunflower oil delivery on the terms CPT Chornomorsk. The appropriate contract was governed by English law and incorporated proforma FOSFA 57. The Client (Seller) performed all the contract terms, but payment for the goods still was not received. Negotiations between the parties were unsuccessful and in vain.

In the process of representing interests, the Client’s Counteragent made procedural pressure, in particular, contested jurisdiction and delayed proceedings by submitting the large set of documents and evidence. However, Interlegal lawyers not only succeeded in proving the jurisdiction but also persuaded arbitration court in grounds for satisfying the claim.

Therefore, while representing the Client’s interests, Interlegal facilitated obtaining FOSFA positive award in the amount exceeding 4 million USD to be payable by the Counteragent to the Client, jointly with interests and arbitration fees.

Interlegal partners Alexey Remeslo and Artem Skorobogatov and junior lawyer Denys Bakaiev led the case.

  • The Buyer failed to fulfill its financial obligations within deadline prescribed by the contract2024.05.23

    A client, seller who entered into contracts with two companies of the same group, applied to Interlegal. The contracts provided supply o...

    show more
  • Limassol Boat Show 20242024.05.15

    We are pleased to announce that on 23-26 May Interlegal will be participating in the ninth edition of the largest boat show in the Eas...

    show more
  • General average due to collision of vessels. What should the cargo owner do?2024.03.18

    Expansion of geography to the Caspian states was and is one of the goals of our company development. Therefore, we are particularly plea...

    show more
  • Misunderstanding and technical errors as the reason for dispute2024.02.12

    A company applied to Interlegal for carrying out claims handling with their counterparty. Due to a simple misunderstanding, business rel...

    show more
  • What are the legal effects of delivering goods of poor quality under CIF contract?2024.02.05

    The Client applied to Interlegal for analysis of potential consequences of delivering mineral fertilizers of poor quality in the framewo...

    show more
  • UPD: what to do if arrest fails at the first time?2023.11.30

    Fresh news by Interlegal: one of the most interesting latest ship arrests! Let us remind: A Cypriot company filed to Interlegal a req...

    show more
  • Bank request again: additional documents and explanations2023.11.20

    Now in the process of transactions banks often asks our Clients to provide documents certifying lawful payment, mainly agreement between...

    show more
  • Forgive and forget: is small demurrage a reasonable excuse for arbitration proceedings?2023.10.26

    The Seller under CIF Contract applied to Interlegal; it delivered goods to the Buyer within the prescribed supply period and performed a...

    show more
  • Freight management flaws: incorrect notices or disputed claims2023.10.23

    Recently, Interlegal law team defended the Client’s interests in a dispute regarding incorrectly calculated demurrage. The case concerne...

    show more
  • Interlegal obtained FOSFA award in favor of the Client in the amount exceeding 4 million USD2023.10.16

    The Client applied to our law team due to non-performance of contract terms, i.e. non-payment for the goods. Parties to the contract...

    show more